Generation unit/Production unit Type Power (MW) Maximum power (MW) Start date End date Publication date Status
REVIN 4 Forced 0.00 202 22/03/2019
21:46:00
22/03/2019
23:01:00
22/03/2019
22:06:12
Active
BATHIE 1 Forced 0.00 100 22/03/2019
21:46:00
22/03/2019
22:47:00
22/03/2019
22:06:08
Withdrawn
DAMPIERRE 1 Forced 0 890 04/03/2019
19:30:00
24/03/2019
15:00:00
22/03/2019
20:39:07
Active
CRUAS 2 Planned 65 915 22/03/2019
19:00:00
22/03/2019
20:00:00
22/03/2019
20:06:07
Active
CHINON 2 Forced 480 905 22/03/2019
20:00:00
23/03/2019
13:00:00
22/03/2019
18:01:12
Active
CHINON 2 Planned 0 905 16/03/2019
03:30:00
22/03/2019
20:00:00
22/03/2019
18:01:08
Active
GRAVELINES 5 Planned 50 910 02/08/2019
23:30:00
03/08/2019
03:00:00
22/03/2019
17:39:07
Active
GRAVELINES 5 Planned 0 910 03/08/2019
03:00:00
09/12/2019
03:00:00
22/03/2019
17:36:06
Active
BELLEVILLE 2 Forced 0 1310 16/03/2019
15:21:00
23/03/2019
23:00:00
22/03/2019
17:33:06
Active
TRICASTIN 4 Planned 0 915 06/04/2019
01:00:00
12/05/2019
02:00:00
22/03/2019
16:42:07
Active

European Regulation 1227/2011 on Wholesale Energy Market Integrity and Transparency (REMIT) requires producers to disclose to the public certain information concerning their assets. On this website you will find selected information related to planned and unplanned unavailability of EDF's production assets as well as other relevant information on the capacity and use of these assets. The unavailabilities planning of production units is EDF’s best estimate at publication time and it is based on the reasonable estimate of the time needed for the achievement of the planned maintenance on each unit.