Flamanville EPR: status update
EDF actively continues to implement the action plan on welds of the main secondary system announced on 25 July 2018. The "hot tests" are now scheduled to commence during the second half of February.
The teams of EDF and of its industrial partners remain fully mobilized to complete the loading of nuclear fuel during the 4th quarter of 2019 under target construction costs for EDF at the commissioning date kept at €10.9 billion1 .
1 In Euros of 2015, excluding interim interests
Contacts
Analysts and investors
Phone: +33 (0) 1 40 42 40 38
Press Office
Phone: +33 (0) 1 40 42 46 37
service-de-presse@edf.fr