Third point, as regards Nuclear New Build, Flamanville 3 reached a significant milestone with the beginning of the system performance testing for the whole plant, in accordance with the timetable announced in September 2015. In Taishan, a new set of key tests has been started with the goal to load fuel in H2 2017 for Taishan 1 and in H1 2018 for Taishan 2.