EDF-2020-00077

  • Current version of the message - v6
    • Status : Active
      Publication date : 06/07/2020 13:47:37
      Start date : 24/04/2020 11:36:18
      Company : EDF
      The Civaux 2 power unit will have to be stopped at least for 5 weeks for modulation by its next maintenance planned in week 5 in year 2021. The positioning of these modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.
  • Earlier version of the message - v5
    • Status : Inactive
      Publication date : 15/06/2020 16:12:49
      Start date : 24/04/2020 11:36:18
      Company : EDF
      The Civaux 2 power unit will have to be stopped at least for 6 weeks for modulation by its next maintenance planned in week 5 in year 2021. The positioning of these modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.
  • Earlier version of the message - v4
    • Status : Inactive
      Publication date : 02/06/2020 10:46:56
      Start date : 24/04/2020 11:36:18
      Company : EDF
      The Civaux 2 power unit will have to be stopped at least for 7 weeks for modulation by its next maintenance planned in week 5 in year 2021. The positioning of these modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.
  • Earlier version of the message - v3
    • Status : Inactive
      Publication date : 22/05/2020 15:58:45
      Start date : 24/04/2020 11:36:18
      Company : EDF
      The Civaux 2 power unit will have to be stopped at least for 8 weeks for modulation by its next maintenance planned in week 5 in year 2021. The positioning of these modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.
  • Earlier version of the message - v2
    • Status : Inactive
      Publication date : 11/05/2020 11:36:02
      Start date : 24/04/2020 11:36:18
      Company : EDF
      The Civaux 2 power unit will have to be stopped at least for 9 weeks for modulation by its next maintenance planned in week 5 in year 2021. The positioning of these modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.
  • Earlier version of the message - v1
    • Status : Inactive
      Publication date : 24/04/2020 11:38:22
      Start date : 24/04/2020 11:36:18
      Company : EDF
      The Civaux 2 power unit will have to be stopped at least for 10 weeks for modulation by its next maintenance planned in week 5 in year 2021. The positioning of these modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.