EDF-2019-00011

  • Current version of the message - v8
    • Status : Active
      Publication date : 03/09/2019 09:35:47
      Start date : 25/01/2019 18:06:11
      Company : EDF
      End of the specific management of modulation weeks for the Tricastin 3 power unit.
  • Earlier version of the message - v7
    • Status : Inactive
      Publication date : 26/08/2019 15:57:37
      Start date : 25/01/2019 18:06:11
      Company : EDF
      The Tricastin 3 power unit will have to be stopped at least for 1 week for modulation by its next maintenance planned in week 10 in year 2020. The positioning of this modulation week is provisional: it will be reassessed and the plant will be restarted if economically justified.
  • Earlier version of the message - v6
    • Status : Inactive
      Publication date : 19/08/2019 13:50:42
      Start date : 25/01/2019 18:06:11
      Company : EDF
      The Tricastin 3 power unit will have to be stopped at least for 2 weeks for modulation by its next maintenance planned in week 10 in year 2020. The positioning of these modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.
  • Earlier version of the message - v5
    • Status : Inactive
      Publication date : 12/08/2019 09:21:08
      Start date : 25/01/2019 18:06:11
      Company : EDF
      The Tricastin 3 power unit will have to be stopped at least for 3 weeks for modulation by its next maintenance planned in week 10 in year 2020. The positioning of these modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.
  • Earlier version of the message - v4
    • Status : Inactive
      Publication date : 15/07/2019 15:41:58
      Start date : 25/01/2019 18:06:11
      Company : EDF
      The Tricastin 3 power unit will have to be stopped at least for 4 weeks for modulation by its next maintenance planned in week 10 in year 2020. The positioning of these modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.
  • Earlier version of the message - v3
    • Status : Inactive
      Publication date : 24/06/2019 09:50:10
      Start date : 25/01/2019 18:06:11
      Company : EDF
      The Tricastin 3 power unit will have to be stopped at least for 3 weeks for modulation by its next maintenance planned in week 10 in year 2020. The positioning of these modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.
  • Earlier version of the message - v2
    • Status : Inactive
      Publication date : 17/06/2019 11:20:48
      Start date : 25/01/2019 18:06:11
      Company : EDF
      The Tricastin 3 power unit will have to be stopped at least for 4 weeks for modulation by its next maintenance planned in week 10 in year 2020. The positioning of these modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.
  • Earlier version of the message - v1
    • Status : Inactive
      Publication date : 25/01/2019 18:06:25
      Start date : 25/01/2019 18:06:11
      Company : EDF
      The Tricastin 3 power unit will have to be stopped at least for 5 weeks for modulation by its next maintenance planned in week 10 in year 2020. The positioning of this modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.