EDF-2019-00010

Be carreful, the RSS feeds is now reduced to the last 15 days
  • Current version of the message - v3
    • Status : Active
      Publication date : 14/05/2019 12:34:30
      Start date : 25/01/2019 18:05:41
      Company : EDF
      The Cruas 3 power unit will have to be stopped at least for 3 weeks for modulation by its next maintenance planned in week 7 in year 2020. The positioning of these modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.
  • Earlier version of the message - v2
    • Status : Inactive
      Publication date : 06/05/2019 14:54:17
      Start date : 25/01/2019 18:05:41
      Company : EDF
      The Cruas 3 power unit will have to be stopped at least for 4 weeks for modulation by its next maintenance planned in week 7 in year 2020. The positioning of these modulation weeks is provisional: it will be reassessed and the plant will be restarted if economically justified.
  • Earlier version of the message - v1
    • Status : Inactive
      Publication date : 25/01/2019 18:05:46
      Start date : 25/01/2019 18:05:41
      Company : EDF
      The Cruas 3 power unit will have to be stopped at least for 5 weeks for modulation by its next maintenance planned in week 7 in year 2020. The positioning of this modulation week is provisional: it will be reassessed and the plant will be restarted if economically justified.