EDF-2019-00009

Be carreful, the RSS feeds is now reduced to the last 15 days
  • Current version of the message - v3
    • Status : Active
      Publication date : 04/04/2019 17:45:45
      Start date : 25/01/2019 18:05:16
      Company : EDF
      Fin de la gestion particulière des semaines d'arrêt pour modulation concernant la tranche de Dampierre 4.
      ----------
      End of the specific management of modulation weeks for the Dampierre 4 power unit.
  • Earlier version of the message - v2
    • Status : Inactive
      Publication date : 25/03/2019 09:46:51
      Start date : 25/01/2019 18:05:16
      Company : EDF
      The Dampierre 4 power unit will have to be stopped at least for 1 week for modulation by its next maintenance planned in week 4 in year 2020. The positioning of this modulation week is provisional: it will be reassessed and the plant will be restarted if economically justified.
  • Earlier version of the message - v1
    • Status : Inactive
      Publication date : 25/01/2019 18:05:29
      Start date : 25/01/2019 18:05:16
      Company : EDF
      The Dampierre 4 power unit will have to be stopped at least for 2 weeks for modulation by its next maintenance planned in week 5 in year 2020. The positioning of this modulation week is provisional: it will be reassessed and the plant will be restarted if economically justified.