- Current version of the outage - v4
- Entity : GenerationName : PALUEL 3Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : ActivePublication date : 28/11/2020 01:31:05Cause : FailureComplementary informations :Between the : 27/11/2020 10:30:00and the : 28/11/2020 02:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWER
The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v3
- Entity : GenerationName : PALUEL 3Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : InactivePublication date : 27/11/2020 20:43:05Cause : FailureComplementary informations :Between the : 27/11/2020 10:30:00and the : 28/11/2020 01:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWER
The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v2
- Entity : GenerationName : PALUEL 3Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : InactivePublication date : 27/11/2020 11:58:07Cause : FailureComplementary informations :Between the : 27/11/2020 10:30:00and the : 27/11/2020 23:00:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWER
The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v1
- Entity : GenerationName : PALUEL 3Sector : NuclearLocation : FranceMarket FranceType : ForcedStatus : InactivePublication date : 27/11/2020 10:37:07Cause : FailureComplementary informations :Between the : 27/11/2020 10:30:00and the : 28/11/2020 10:30:000 MWMW AVAILABLE POWER1330 MWMW MAXIMUM POWER
The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.