- Current version of the outage - v18
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : ActivePublication date : 02/12/2020 10:28:11Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 900 MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 900 MWBetween the : 23/11/2020 19:30:00and the : 02/12/2020 22:00:00785 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v17
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 30/11/2020 21:40:07Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 900 MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 900 MWBetween the : 23/11/2020 19:30:00and the : 04/12/2020 02:00:00785 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v16
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 30/11/2020 04:37:06Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 790 MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 790 MWBetween the : 23/11/2020 19:30:00and the : 04/12/2020 02:00:00370 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v15
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 29/11/2020 23:37:06Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 790 MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 790 MWBetween the : 23/11/2020 19:30:00and the : 02/12/2020 13:00:00370 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v14
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 28/11/2020 21:52:06Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 790 MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 790 MWBetween the : 23/11/2020 19:30:00and the : 02/12/2020 07:00:00370 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v13
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 28/11/2020 05:31:05Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 790 MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 790 MWBetween the : 23/11/2020 19:30:00and the : 01/12/2020 03:30:00370 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v12
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 28/11/2020 04:43:05Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 603 MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 603 MWBetween the : 23/11/2020 19:30:00and the : 01/12/2020 06:00:00370 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v11
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 27/11/2020 22:25:06Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 603 MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 603 MWBetween the : 23/11/2020 19:30:00and the : 30/11/2020 19:00:00370 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v10
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 26/11/2020 23:58:06Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 603 MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 603 MWBetween the : 23/11/2020 19:30:00and the : 30/11/2020 09:00:00370 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v9
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 25/11/2020 19:52:06Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 343 MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 343 MWBetween the : 23/11/2020 19:30:00and the : 30/11/2020 01:00:00370 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v8
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 25/11/2020 18:40:07Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 343 MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 343 MWBetween the : 23/11/2020 19:30:00and the : 30/11/2020 08:00:00370 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v7
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 25/11/2020 07:31:06Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 786 MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 786 MWBetween the : 23/11/2020 19:30:00and the : 30/11/2020 22:00:00370 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v6
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 24/11/2020 07:19:06Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 786 MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 786 MWBetween the : 23/11/2020 19:30:00and the : 28/11/2020 12:30:00370 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v5
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 24/11/2020 01:52:06Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 372 MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 372 MWBetween the : 23/11/2020 19:30:00and the : 28/11/2020 12:30:00203 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v4
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 23/11/2020 23:22:06Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 186MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 186 MWBetween the : 23/11/2020 19:30:00and the : 28/11/2020 14:30:00109 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v3
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 23/11/2020 22:08:06Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 186MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 186 MWBetween the : 23/11/2020 19:30:00and the : 28/11/2020 11:00:00109 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v2
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 23/11/2020 21:34:15Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 110MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 110 MWBetween the : 23/11/2020 19:30:00and the : 28/11/2020 11:00:0050 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.
- Earlier version of the outage - v1
- Entity : GenerationName : CRUAS 4Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 23/11/2020 19:55:07Cause : Complementary informationsComplementary informations :
Remontée par paliers en cours
Prochain palier : 110MW
---------------------------------------------------------------------------------
Unit is currently ramping up by steps
Next step : 110 MWBetween the : 23/11/2020 19:30:00and the : 28/11/2020 11:00:0050 MWMW AVAILABLE POWER915 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset. In case of overlapping outages, whether forced or planned, the practice is to use the lowest available power for each overlapping period.