GRAVELINES 3

  • Current version of the outage - v2
    • Entity : Generation
      Name : GRAVELINES 3
      Sector : Nuclear
      Location : France
      Market France
      Type : Forced
      Status : Active
      Publication date : 24/12/2017 00:15:15
      Cause : Failure
      Complementary informations :
      Between the : 23/12/2017 22:56:00
      and the : 24/12/2017 00:00:00
      800 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v1
    • Entity : Generation
      Name : GRAVELINES 3
      Sector : Nuclear
      Location : France
      Market France
      Type : Forced
      Status : Inactive
      Publication date : 23/12/2017 23:27:10
      Cause : Failure
      Complementary informations :
      Between the : 23/12/2017 22:56:00
      and the : 24/12/2017 22:55:00
      800 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.