GRAVELINES 5

  • Current version of the outage - v7
    • Entity : Generation
      Name : GRAVELINES 5
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Active
      Publication date : 21/03/2019 14:19:42
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 07/11/2020 02:00:00
      and the : 11/01/2021 02:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v6
    • Entity : Generation
      Name : GRAVELINES 5
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 22/11/2018 17:36:27
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 24/10/2020 02:00:00
      and the : 28/12/2020 02:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v5
    • Entity : Generation
      Name : GRAVELINES 5
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 03/08/2018 16:14:22
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 03/10/2020 02:00:00
      and the : 07/12/2020 02:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v4
    • Entity : Generation
      Name : GRAVELINES 5
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 22/12/2017 15:44:17
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 19/09/2020 02:00:00
      and the : 18/11/2020 02:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v3
    • Entity : Generation
      Name : GRAVELINES 5
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 16/11/2017 17:25:21
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 12/09/2020 02:00:00
      and the : 11/11/2020 02:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v2
    • Entity : Generation
      Name : GRAVELINES 5
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 11/08/2017 17:44:29
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 18/07/2020 02:00:00
      and the : 16/09/2020 02:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v1
    • Entity : Generation
      Name : GRAVELINES 5
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 18/07/2017 02:31:01
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      -----------------------------------------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 18/07/2020 02:00:00
      and the : 19/09/2020 02:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.