Current version of the outage - v19
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : ActivePublication date : 04/12/2019 07:06:07Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 03/08/2019 02:22:00and the : 10/01/2020 23:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v18
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 27/11/2019 17:48:14Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 03/08/2019 02:22:00and the : 06/01/2020 23:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v17
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 24/11/2019 17:42:08Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 03/08/2019 02:22:00and the : 02/01/2020 23:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v16
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 18/11/2019 16:54:14Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 03/08/2019 02:22:00and the : 29/12/2019 23:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v15
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 12/11/2019 17:12:23Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 03/08/2019 02:22:00and the : 25/12/2019 23:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v14
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 08/11/2019 21:18:11Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 03/08/2019 02:22:00and the : 21/12/2019 23:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v13
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 24/10/2019 09:42:15Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 03/08/2019 02:22:00and the : 17/12/2019 23:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v12
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 07/10/2019 18:33:11Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 03/08/2019 02:22:00and the : 13/12/2019 23:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v11
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 03/08/2019 02:30:18Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 03/08/2019 02:22:00and the : 09/12/2019 03:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v10
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 22/03/2019 17:36:06Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 03/08/2019 03:00:00and the : 09/12/2019 03:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v9
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 27/12/2018 09:21:19Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 03/08/2019 02:00:00and the : 09/12/2019 02:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v8
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 28/09/2018 14:01:10Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 03/08/2019 02:00:00and the : 26/11/2019 02:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v7
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 03/08/2018 16:14:18Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 27/07/2019 02:00:00and the : 19/11/2019 02:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v6
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 22/12/2017 15:43:17Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
-------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 27/07/2019 02:00:00and the : 09/11/2019 02:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v5
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 26/01/2017 14:05:34Cause : Complementary informationsComplementary informations :
After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
-----------------------------------------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 15/06/2019 02:00:00and the : 28/09/2019 02:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v4
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 30/11/2016 15:47:18Cause : Complementary informationsComplementary informations :
After its re-coupling, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
-----------------------------------------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 08/06/2019 02:00:00and the : 21/09/2019 02:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v3
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 12/10/2016 15:51:42Cause : Complementary informationsComplementary informations :
After its re-coupling, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
-----------------------------------------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 20/07/2019 02:00:00and the : 20/08/2019 02:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v2
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 25/04/2016 17:09:03Cause : Complementary informationsComplementary informations :
After its re-coupling, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
-----------------------------------------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 29/09/2018 02:00:00and the : 03/12/2018 02:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-
-
Earlier version of the outage - v1
-
Entity : GenerationName : GRAVELINES 5Sector : NuclearLocation : FranceMarket FranceType : PlannedStatus : InactivePublication date : 25/09/2015 18:42:13Cause : Complementary informationsComplementary informations :
After its re-coupling, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
-----------------------------------------------------------------------
Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.Between the : 01/09/2018 02:00:00and the : 05/11/2018 02:00:000 MWMW AVAILABLE POWER910 MWMW MAXIMUM POWERThe unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.
-