BLAYAIS 2

  • Current version of the outage - v14
    • Entity : Generation
      Name : BLAYAIS 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Active
      Publication date : 17/04/2018 22:24:10
      Cause : Complementary informations
      Complementary informations :
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Premier palier à atteindre : 375 MW
      ----------------------------------------------------
      After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      First threshold after restart : 375 MW
      Between the : 10/03/2018 00:00:00
      and the : 18/04/2018 00:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v13
    • Entity : Generation
      Name : BLAYAIS 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 17/04/2018 21:42:09
      Cause : Complementary informations
      Complementary informations :
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Premier palier à atteindre : 375 MW
      ----------------------------------------------------
      After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      First threshold after restart : 375 MW
      Between the : 10/03/2018 00:00:00
      and the : 17/04/2018 22:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v12
    • Entity : Generation
      Name : BLAYAIS 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 17/04/2018 08:30:10
      Cause : Complementary informations
      Complementary informations :
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Premier palier à atteindre : 375 MW
      ----------------------------------------------------
      After its restart, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      First threshold after restart : 375 MW
      Between the : 10/03/2018 00:00:00
      and the : 17/04/2018 23:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v11
    • Entity : Generation
      Name : BLAYAIS 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 14/04/2018 17:06:09
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 10/03/2018 00:00:00
      and the : 18/04/2018 23:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v10
    • Entity : Generation
      Name : BLAYAIS 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 03/04/2018 13:30:11
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 10/03/2018 00:00:00
      and the : 21/04/2018 02:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v9
    • Entity : Generation
      Name : BLAYAIS 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 19/02/2018 13:06:11
      Cause : Complementary informations
      Complementary informations :
      Durée d'arrêt susceptible d'être affectée par la mise en service industrielle de nouveaux procédés sur un générateur de vapeur. The duration of the unavailability may change according to the commissioning of new industrial processes on the steam generator.
      Between the : 10/03/2018 00:00:00
      and the : 21/04/2018 02:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v8
    • Entity : Generation
      Name : BLAYAIS 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 26/01/2018 11:03:51
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 10/03/2018 00:00:00
      and the : 21/04/2018 02:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v7
    • Entity : Generation
      Name : BLAYAIS 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 16/01/2018 09:57:13
      Cause : Complementary informations
      Complementary informations :
      Durée d'arrêt susceptible d'être affectée par la mise en service industrielle de nouveaux procédés sur un générateur de vapeur.
      The duration of the unavailability may change according to the commissioning of new industrial processes on the steam generator.
      Between the : 10/03/2018 00:00:00
      and the : 11/04/2018 02:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v6
    • Entity : Generation
      Name : BLAYAIS 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 11/08/2017 16:54:28
      Cause : Complementary informations
      Complementary informations :
      Durée d'arrêt susceptible d'être affectée par la mise en service industrielle de nouveaux procédés sur un générateur de vapeur.
      The duration of the unavailability may change according to the commissioning of new industrial processes on the steam generator.
      Between the : 10/03/2018 02:00:00
      and the : 11/04/2018 02:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v5
    • Entity : Generation
      Name : BLAYAIS 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 19/08/2016 15:38:15
      Cause : Complementary informations
      Complementary informations :
      After its re-coupling, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      -----------------------------------------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 10/03/2018 02:00:00
      and the : 12/04/2018 02:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v4
    • Entity : Generation
      Name : BLAYAIS 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 08/07/2016 17:00:22
      Cause : Complementary informations
      Complementary informations :
      After its re-coupling, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      -----------------------------------------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 17/02/2018 02:00:00
      and the : 22/03/2018 02:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v3
    • Entity : Generation
      Name : BLAYAIS 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 01/10/2015 12:15:08
      Cause : Complementary informations
      Complementary informations :
      After its re-coupling, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      -----------------------------------------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 17/02/2018 02:00:00
      and the : 21/03/2018 02:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v2
    • Entity : Generation
      Name : BLAYAIS 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 31/07/2015 18:06:10
      Cause : Complementary informations
      Complementary informations :
      After its re-coupling, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      -----------------------------------------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 17/02/2018 02:00:00
      and the : 21/03/2018 03:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v1
    • Entity : Generation
      Name : BLAYAIS 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 22/04/2015 15:27:03
      Cause : Complementary informations
      Complementary informations :
      After its re-coupling, the plant will gradually return by various load threshold to full power. The ramp-up period will take at least 48 hours.
      -----------------------------------------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 24/02/2018 02:00:00
      and the : 25/03/2018 03:00:00
      0 MW
      MW AVAILABLE POWER
      910 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.