CHINON 2

  • Current version of the outage - v21
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Active
      Publication date : 14/10/2017 17:00:15
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      First threshold after restart : 180 MW
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Premier palier à atteindre : 180 MW
      Between the : 26/08/2017 01:00:00
      and the : 14/10/2017 12:20:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v20
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 14/10/2017 16:24:08
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      First threshold after restart : 367 MW
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Premier palier à atteindre : 367 MW
      Between the : 26/08/2017 01:00:00
      and the : 14/10/2017 12:20:00
      180 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v19
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 14/10/2017 12:36:11
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      First threshold after restart : 181MW
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Premier palier à atteindre : 181MW
      Between the : 26/08/2017 01:00:00
      and the : 14/10/2017 12:20:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v18
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 13/10/2017 15:12:07
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      First threshold after restart : 181MW
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Premier palier à atteindre : 181MW
      Between the : 26/08/2017 01:00:00
      and the : 14/10/2017 16:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v17
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 11/10/2017 10:06:08
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      First threshold after restart : 181MW
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Premier palier à atteindre : 181MW
      Between the : 26/08/2017 01:00:00
      and the : 13/10/2017 23:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v16
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 06/10/2017 09:12:17
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      First threshold after restart : 181MW
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Premier palier à atteindre : 181MW
      Between the : 26/08/2017 01:00:00
      and the : 12/10/2017 23:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v15
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 01/10/2017 20:06:12
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      First threshold after restart : 181MW
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Premier palier à atteindre : 181MW
      Between the : 26/08/2017 01:00:00
      and the : 08/10/2017 23:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v14
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 01/10/2017 07:57:06
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      First threshold after restart : 181MW
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Premier palier à atteindre : 181MW
      Between the : 26/08/2017 01:00:00
      and the : 03/10/2017 23:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v13
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 28/09/2017 20:51:07
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 26/08/2017 01:00:00
      and the : 03/10/2017 23:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v12
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 25/09/2017 20:12:06
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 26/08/2017 01:00:00
      and the : 01/10/2017 23:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v11
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 20/09/2017 17:48:08
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 26/08/2017 01:00:00
      and the : 28/09/2017 23:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v10
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 25/08/2017 11:22:10
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 26/08/2017 01:00:00
      and the : 25/09/2017 02:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v9
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 21/08/2017 11:21:06
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 26/08/2017 00:30:00
      and the : 25/09/2017 02:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v8
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 11/08/2017 16:58:34
      Cause : Complementary informations
      Complementary informations :
      After its restart, the plant will gradually return by various load thresholds to full power. The ramp-up period will take at least 48 hours.
      -------------------------------------
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée durera au moins 48h.
      Between the : 26/08/2017 02:00:00
      and the : 25/09/2017 02:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v7
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 05/01/2017 10:52:06
      Cause : Complementary informations
      Complementary informations :
      After its re-coupling, the plant will gradually return by various load threshold to full power. The ramp-up period may take several days.
      --
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée peut prendre plusieurs jours.
      Between the : 26/08/2017 00:30:00
      and the : 26/09/2017 02:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v5
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 19/08/2016 15:45:25
      Cause : Complementary informations
      Complementary informations :
      After its re-coupling, the plant will gradually return by various load threshold to full power. The ramp-up period may take several days.
      --
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée peut prendre plusieurs jours.
      Between the : 26/08/2017 02:00:00
      and the : 27/09/2017 02:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v4
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 01/03/2016 17:54:07
      Cause : Complementary informations
      Complementary informations :
      After its re-coupling, the plant will gradually return by various load threshold to full power. The ramp-up period may take several days.
      --
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée peut prendre plusieurs jours.
      Between the : 22/04/2017 02:00:00
      and the : 24/05/2017 02:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v3
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 29/01/2016 15:33:06
      Cause : Complementary informations
      Complementary informations :
      After its re-coupling, the plant will gradually return by various load threshold to full power. The ramp-up period may take several days.
      --
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée peut prendre plusieurs jours.
      Between the : 22/04/2017 02:00:00
      and the : 23/05/2017 02:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v2
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 31/07/2015 17:45:10
      Cause : Complementary informations
      Complementary informations :
      After its re-coupling, the plant will gradually return by various load threshold to full power. The ramp-up period may take several days.
      --
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée peut prendre plusieurs jours.
      Between the : 01/04/2017 02:00:00
      and the : 02/05/2017 02:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.

  • Earlier version of the outage - v1
    • Entity : Generation
      Name : CHINON 2
      Sector : Nuclear
      Location : France
      Market France
      Type : Planned
      Status : Inactive
      Publication date : 11/02/2015 11:09:52
      Cause : Complementary informations
      Complementary informations :
      After its re-coupling, the plant will gradually return by various load threshold to full power. The ramp-up period may take several days.
      --
      Après son recouplage, la tranche remontera progressivement par palier de charge à sa pleine puissance. La remontée peut prendre plusieurs jours.
      Between the : 01/04/2017 02:00:00
      and the : 01/05/2017 02:00:00
      0 MW
      MW AVAILABLE POWER
      905 MW
      MW MAXIMUM POWER

      The unavailabilities planning of a production unit is EDF’s best estimate at the time of publication and it is based on an estimate of the duration reasonably required for the planned works or events liable to affect the asset.