The first of two EPR reactors at China's Taishan nuclear power plant enters into commercial operation | EDF Asie

This last milestone was reached on Thursday 13 th of December 2018 after the final statutory functional test of continuous operation at full power for 168 hours. The successful outcome of this test marks the achievement of all prerequisite conditions for the reactor's safe operation... The use of this operating experience was a crucial factor in successfully completing the initial phases of the Taishan 1 construction project.

  1. Edf.fr
  2. EDF in Asia
  3. News

The second EPR reactor at China's Taishan nuclear power plant about to enter into commercial operation | EDF Asie

Unit 2 of the Taishan nuclear power plant will enter into commercial operation on Saturday the 7th of September 2019, following statutory functional test of continuous operation at full power for 168 hours, which started on Saturday the 30th of August at 17: 15 local time... More than 15 000 workers were mobilised during the busiest periods of the construction phase.

  1. Edf.fr
  2. EDF in Asia
  3. News

EDF has completed the cold functional test phase for the Flamanville EPR | EDF FR

EDF has completed the cold functional test phase for the Flamanville EPR... On 6 January 2018, EDF completed the cold functional test phase for the Flamanville EPR... This cold functional test phase, which started on 18 December 2017, saw the successful completion of the leak performance test on the primary system at a pressure greater than 240 bar (higher than the pressure of this system in operation).

  1. Edf.fr
  2. The EDF Group
  3. Dedicated sections
  4. Journalists
  5. All press releases

Flamanville EPR: EDF has adopted a scenario for upgrading the main secondary system penetration welds with robots and has adjusted the construction schedule and estimated cost accordingly(1) | EDF FR

The second hot functional test phase has started on site... At the same time, the second hot functional test phase was started on 21 September 2019 and will last until the end of 2019 . These tests are performed on the plant in normal operating conditions.

  1. Edf.fr
  2. The EDF Group
  3. Dedicated sections
  4. Journalists
  5. All press releases
  6. Flamanville EPR: EDF has adopted a scenario for upgrading the main secondary system penetration welds with robots and has adjusted the construction schedule and estimated cost accordingly
  7. (1)

Quarterly Financial Information - 3rd quarter 2019 | EDF FR

Flamanville)3 (4 :estimated construction cost revised to euros 12 4bn (5) with fuel loading expected at end- 2022, start of the second hot functional test phase on site. Fessenheim (6) :protocol agreement whereby the State will compensate EDF for the early closure of the power plant .